GAIL's LPG pipeline and implementation schedule

Vol 5, PW 25 (13 Feb 02) News in Brief
     

GAIL is putting in place two key pipeline projects (one each in eastern and western India) to transport LPG and a Delhi-Mumbai telecommunications project.

See below: Project Vizag-Secunderabad pipeline Jamnagar-Loni phase 2 Telecom project phase 2 Location Vizag-Secunderabad Kandla-Samakhiyali Delhi-Mumbai Date of approval 27th Feb. 2001 31st Jan.

2001 1st March 2001 Date of completion 27th June 2003 15th Sept. 2002 15th Dec.

2002 Date of commissioning 27th Aug. 2003 30th Sept.

2002 31st Dec. 2002 Capital cost (Rs cr) 490.65 70.00 199.20 Capacity 1.16m t/y 0.8m t/y 10gbps Products LPG LPG Bandwidth capacity